OANG-Camp Sherman

Project: Ohio Army National Guard Camp Sherman Add/Alt (LEED Silver Certification)

Owner: Ohio Army National Guard

Year: 2011-14

Cost: $2,700,000

Project Manager: Hamid Mukhtar, PhD, PE

Scope: This project provided a 9,848 SF Field Maintenance Shop Add/Alt Facility of permanent type construction. A maintenance building adds/alt with maintenance work bays, administrative and personnel work areas. Work also included a new standing seam metal Roof.

Work was performed in time to meet ownerís schedule. Liquid applied Vehicular traffic deck coating was selected to fit the project budget. Existing concrete and metal connections were sandblasted to achieve desired surfaces to adhere the coating. QA/QC was enforced during construction to make sure all coating was installed as per manufacturerís recommendation so that a 5 year water proofing warranty can be obtained.

ODOT Athens FSMF

Project: ODOT Athens Full Service Maintenance Facility (Design-Build)

Owner: Ohio Department of Transportation

Year: 2013

Cost: $7,500,000

Project Manager: Hamid Mukhtar, PhD, PE

Scope: Star was Criteria Architect for a Design Build for 13 acre, with 7,500 G.S.F. office/vehicle maintenance building, 19,000 G.S.F. truck storage building, new site utilities, new fueling station, 2,500 G.S.F. fabric covered material storage building, 8,000 G.S.F. salt storage building, 3,920 G.S.F. cold storage building, monopole communications antenna, site grading, Driveway and parking, and fence and gates.

COTA Madison

Project: ODOT Madison Full Service Maintenance Facility

Owner: Ohio Department of Transportation

Year: 2013

Cost: $8,000,000

Project Manager: Hamid Mukhtar, PhD, PE

Scope: Design Build for 15 acre, with 6,080 sq. ft. vehicle maintenance building, 23,003 sq. ft. truck storage building, 3,676 sq. ft. office Building, new site utilities, new fueling station, 1,857 sq. ft. fabric covered material storage building, 9,100 sq. ft. salt storage building, 6,804 sq. ft. cold storage building, monopole communications antenna, site grading, three ponds, Driveway and parking, and fence and gates. In addition to building permits, Star secured EPA permit for this facility.

ODOT Fayette FSMF

Project: ODOT Fayette Full Service Maintenance Facility

Owner: Ohio Department of Transportation

Year: 2015-16

Cost: $8,610,000

Project Manager: Ali Alghothani PhD, PE

Scope: The Full Service Maintenance Facility will be located on the existing site and will contain combinations of multiple functional areas (site utilities, site grading, parking lots, office / maintenance building, truck parking building, salt storage structure, material storage building, cold storage building, brine maker with storage and calcium tanks, and above ground fuel storage tank with dispensers), and selective demolition of existing facilities.

Buildings Include Truck Storage, Administrative Section, Mechanical Services Section, Cold Storage Structure, Salt Storage Structure, Material Storage Structure, Above Ground Fuel Storage Tank, Vehicle Wash Bay, Brine/Calcium System