Project: BWC Tower 5th Floor Renovation
Owner: Ohio Department of Youth Services
Year: 2011
Cost: $800,000
Project Manager: Hamid Mukhtar, PhD, PE
Scope: 5th Floor renovations for Department of Youth Services. Tenant work to include installation of new partitions, doors and side lights as well as the coordination of the installation of systems furniture to create new administrative offices suite. STAR consultants scope included Code compliance analysis, coordination of the demolition work.
This project was on an extremely restrictive time schedule which STAR Consultants provided advanced coordination with Code and Permitting agencies and ìWalk Throughî of State Agency reviews.
Work also included Fire Supressor System Upgrade.